United States › Grid › Interconnection queues › Indiana
BATTERY STORAGE · PJMBattery storage project AH1-302, Pulaski County
Battery storage project AH1-302, Pulaski County is a 75.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Pulaski County, Indiana, connecting to AEP.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-302
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- Bottlebrush Solar Energy LLC
- Connection point (POI)
- Olive - Reynolds 345 kV
- Location
- Pulaski County, Indiana
- Technology
- Battery: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 25 February 2025
- Proposed online date
- December 2025
Location
Marker shows the centre of Pulaski County; the queue data does not give exact sites.
Other requests in Pulaski County
- Mammoth South Energy CenterSolar · 300 MW · agreement signed
- Mammoth Central Energy CenterSolar · 300 MW · agreement signed
- Mammoth Central II Energy CenterSolar · 300 MW · agreement signed
- Mayapple SolarSolar · 260 MW · agreement signed
- Moss Creek SolarSolar · 200 MW · agreement signed
- Solar project J2846, Pulaski CountySolar · 700 MW · in study
- Solar project J2849, Pulaski CountySolar · 245 MW · in study
- Battery storage project AH2-233, Pulaski CountyBattery storage · 100 MW · in study
- Battery storage project AH1-482, Pulaski CountyBattery storage · 78.0 MW · in study
- Solar + storage project J3119, Pulaski CountySolar + storage · 350 MW · withdrawn
- Solar project AF2-190, Pulaski CountySolar · 260 MW · withdrawn
- Solar project J1726, Pulaski CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem