BATTERY STORAGE · PJM

Battery storage project AH2-233, Pulaski County

Battery storage project AH2-233, Pulaski County is a 100 MW battery storage request in interconnection study in the PJM interconnection queue, in Pulaski County, Indiana, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-233
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Olive - Reynolds 345 kV
Location
Pulaski County, Indiana
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
9 March 2022
Proposed online date
December 2026

Location

Marker shows the centre of Pulaski County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Pulaski County