United States › Grid › Interconnection queues › Indiana
SOLAR · MISOSolar project J1743, Miami County
Solar project J1743, Miami County is a 293 MW solar request in interconnection study in the MISO interconnection queue, in Miami County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusIn planning
- PlanningQueued Apr 2022 (current stage)
- ConsentedDec 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1743
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Deedsville 345 kV Substation
- Location
- Miami County, Indiana
- Technology
- Solar: 293 MW
- Total requested
- 293 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 6 April 2022
- Agreement signed
- 5 December 2025
- Proposed online date
- August 2026
Location
Marker shows the centre of Miami County; the queue data does not give exact sites.
Other requests in Miami County
- Solar project J3719, Miami CountySolar · 200 MW · in study
- Solar project J2307, Miami CountySolar · 130 MW · in study
- Solar project J2709, Miami CountySolar · 228 MW · withdrawn
- Onshore wind project J1018, Miami CountyOnshore wind · 150 MW · withdrawn
- Battery storage project J1678, Miami CountyBattery storage · 74.7 MW · withdrawn
- Solar project J3390, Miami CountySolar · 37.0 MW · withdrawn
- Battery storage project J2308, Miami CountyBattery storage · 35.0 MW · withdrawn
- Onshore wind project J1150, Miami CountyOnshore wind · 30.0 MW · withdrawn
- Solar + storage project J2778, Miami CountySolar + storage · 15.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem