United States › Grid › Interconnection queues › Indiana

SOLAR · MISO

Solar project J2307, Miami County

Solar project J2307, Miami County is a 130 MW solar request in interconnection study in the MISO interconnection queue, in Miami County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2307
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Greentown - Walton. 230.0kV
Location
Miami County, Indiana
Technology
Solar: 130 MW
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
23 March 2022
Proposed online date
October 2025

Location

Marker shows the centre of Miami County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Miami County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem