Interconnection queue in South Dakota

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown489,628 MW
Active in queue9,628 MW48 requests
Agreement signed3,497 MW20 requests
Withdrawn24960.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

48 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3941, Deuel County
Gas
1,144 MWIn study Deuel, SDMISO Mar 2025target 2030
Solar project J3964, Brookings County
Solar
490 MWIn study Brookings, SDMISO Apr 2025target 2030
Solar project J3963, Brookings County
Solar
490 MWIn study Brookings, SDMISO Apr 2025target 2030
Coal project BHBE G11, Campbell County
Coal
475 MWAgreement signed Campbell, SDWest Sep 2011target 2011
Wind + storage project J3468, Day County
Wind + storage
300 MWIn study Day, SDMISO Apr 2024target 2028
Onshore wind project GEN-2017-014, Haakon County
Onshore wind
300 MWAgreement signed Haakon, SDSPP May 2017target 2027
Coal project BHBE G4, Campbell County
Coal ยท Basin Electric
300 MWAgreement signed Campbell, SDWest Jan 2005target 2011
Solar project BHBE G19, Campbell County
Solar
300 MWAgreement signed Campbell, SDWest May 2022target 2024
Solar + storage project GEN-2024-035, Brown County
Solar + storage
270 MWIn study Brown, SDSPP Oct 2024target 2027
Onshore wind project GEN-2017-175, Turner County
Onshore wind
270 MWAgreement signed Turner, SDSPP Nov 2017target 2028
Gas project E0034, Brookings County
Gas ยท Basin Electric Power Cooperative
265 MWIn study Brookings, SDMISO Aug 2025target 2027
Coal project BHBE G1, Campbell County
Coal ยท Basin Electric
250 MWAgreement signed Campbell, SDWest Feb 2001target 2011
Battery storage project J4153, Grant County
Battery storage
250 MWIn study Grant, SDMISO Oct 2025target 2030
Onshore wind project J1485, Deuel County
Onshore wind
250 MWIn study Deuel, SDMISO Apr 2019target 2022
Onshore wind project GEN-2024-285, Clark County
Onshore wind
250 MWIn study Clark, SDSPP Mar 2025target 2030
Solar project BHBE G20, Dawes County
Solar
250 MWAgreement signed Dawes, SDWest Jul 2022target 2025
Battery storage project J4081, Grant County
Battery storage
250 MWIn study Grant, SDMISO Oct 2025target 2030
Battery storage project J2852, Roberts County
Battery storage
200 MWIn study Roberts, SDMISO Sep 2022target 2025
Onshore wind project GI-0901, Clark County
Onshore wind ยท Crocker Wind
200 MWAgreement signed Clark, SDWest Jan 2009target 2019
Onshore wind project BHBE G21, Campbell County
Onshore wind
200 MWAgreement signed Campbell, SDWest Aug 2022target 2025
Onshore wind project BHBE G7, Campbell County
Onshore wind ยท Third Planet Wind
200 MWAgreement signed Campbell, SDWest Oct 2007target 2010
Onshore wind project J722, Codington County
Onshore wind
200 MWUnder construction Codington, SDMISO Jun 2017target 2023
Onshore wind project J3420, Mcpherson County
Onshore wind
200 MWIn study Mcpherson, SDMISO Mar 2024target 2028
Onshore wind project J3428, Mcpherson County
Onshore wind
200 MWIn study Mcpherson, SDMISO Mar 2024target 2028
Onshore wind project GI-1501, Bon Homme County
Onshore wind
200 MWIn study Bon Homme, SDWest Feb 2015
Solar project GEN-2024-283, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Solar project GEN-2024-282, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Other project J3400, Deuel County
Other
142 MWIn study Deuel, SDMISO Mar 2024target 2028
Gas project ERAS-2025-035, Brown County
Gas
138 MWIn study Brown, SDSPP Oct 2025target 2029
Onshore wind project J3546, Lincoln County
Onshore wind
120 MWIn study Lincoln, SDMISO Apr 2024target 2028
Surplus; J442
Other
120 MWIn study Codington, SDMISO Oct 2023target 2026
Surplus; G736
Other
120 MWIn study Codington, SDMISO Oct 2023target 2026
Gas project BHBE G25, Pennington County
Gas ยท Black Hills Power Inc.
115 MWIn study Pennington, SDWest Jun 2024target 2026
Solar project BHBE G23, Oglala Lakota County
Solar
110 MWAgreement signed Oglala Lakota, SDWest Nov 2022target 2026
Onshore wind project GI-1401, Butte County
Onshore wind
103 MWAgreement signed Butte, SDWest Jan 2014
Coal project BHBE G2, Campbell County
Coal ยท Black Hills Generation
100 MWAgreement signed Campbell, SDWest Feb 2001target 2010
Coal project BHBE G5, Campbell County
Coal ยท Basin Electric
100 MWAgreement signed Campbell, SDWest May 2005target 2011
Onshore wind project GI-1505, Brown County
Onshore wind
99.0 MWIn study Brown, SDWest Apr 2015
Onshore wind project GEN-2016-087, Campbell County
Onshore wind
98.9 MWAgreement signed Campbell, SDSPP Jul 2016target 2026
Solar project BHBE G15, Meade County
Solar ยท Vedauwoo Holdings Black Hills 1 LLC
80.0 MWAgreement signed Meade, SDWest May 2021target 2024
Solar project J1169, Mccook County
Solar
50.0 MWAgreement signed Mccook, SDMISO Mar 2018target 2024
Solar project J1312, Mccook County
Solar
50.0 MWAgreement signed Mccook, SDMISO Apr 2019target 2025
Coal project BHBE G3, Campbell County
Coal ยท Basin Electric
40.0 MWAgreement signed Campbell, SDWest Aug 2004target 2011
Solar project BHBE G22, Meade County
Solar
20.0 MWAgreement signed Meade, SDWest Oct 2022target 2024
Onshore wind project GEN-2025-GR4, Aurora County
Onshore wind
10.8 MWIn study Aurora, SDSPP Oct 2025
Gas project 456, Brown County
Gas
5.0 MWIn study Brown, SDWest Feb 2024target 2025
Gas project 462, Beadle County
Gas
2.0 MWIn study Beadle, SDWest Jun 2024target 2025
Gas project 463, Beadle County
Gas
0.5 MWIn study Beadle, SDWest Jun 2024target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)