United States › Grid › Interconnection queues › South Dakota
ONSHORE WIND · SPPOnshore wind project GEN-2024-285, Clark County
Onshore wind project GEN-2024-285, Clark County is a 250 MW onshore wind request in interconnection study in the SPP interconnection queue, in Clark County, South Dakota, connecting to BEPC.
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-285
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Crocker 345 kV Substation
- Location
- Clark County, South Dakota
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2030
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Clark County
- Onshore wind project GI-0901, Clark CountyOnshore wind · 200 MW · agreement signed
- Onshore wind project GI-1309, Clark CountyOnshore wind · 19.5 MW · built
- Onshore wind project 110, Clark CountyOnshore wind · 19.5 MW · built
- Other project GI-0218, Clark CountyOther · 7.5 MW · built
- Onshore wind project GEN-2018-035, Clark CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1594, Clark CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J458, Clark CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J730, Clark CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project J729, Clark CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project 107, Clark CountyOnshore wind · 99.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem