United States › Grid › Interconnection queues › South Dakota
ONSHORE WIND · WESTOnshore wind project 110, Clark County
Onshore wind project 110, Clark County is a 19.5 MW onshore wind request built and operating in the West interconnection queue, in Clark County, South Dakota, connecting to NorthWestern Energy.
Request details
- Queue ID
- 110
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Clark Junction Substation
- Location
- Clark County, South Dakota
- Technology
- Wind: 19.5 MW
- Total requested
- 19.5 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study System Impact Study
- Queue status
- Operational
- Entered queue
- 20 October 2009
- Proposed online date
- December 2012
- Came online
- December 2012
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Clark County
- Onshore wind project GI-0901, Clark CountyOnshore wind · 200 MW · agreement signed
- Onshore wind project GEN-2024-285, Clark CountyOnshore wind · 250 MW · in study
- Onshore wind project GI-1309, Clark CountyOnshore wind · 19.5 MW · built
- Other project GI-0218, Clark CountyOther · 7.5 MW · built
- Onshore wind project GEN-2018-035, Clark CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1594, Clark CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J458, Clark CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J730, Clark CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project J729, Clark CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project 107, Clark CountyOnshore wind · 99.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem