Line sections1,347mapped segments
Route length19,799 km12,302 mi
345 kV and above2,321 kmthe backbone
Owners18utilities and others

Map

Loading lines…
345 kV220–287 kV100–161 kVUnder 100 kVVoltage not reported

Longest high-voltage lines

220 kV and above, highest voltage first
BetweenVoltageLengthOwnerState
Antelope Valley Station – Broadland345 kV481 km Owner not reportedSD, ND
Leland Olds – Fort Thompson345 kV392 km WAPA-- Western Area Power AdministrationSD, ND
Leland Olds – Groton345 kV342 km Montana-dakota Utilities CoSD, ND
Ellendale 345 Kv345 kV212 km Otter Tail CompanyND, SD
Fort Thompson345 kV198 km WAPA-- Western Area Power AdministrationSD, NE
Sioux City – Split Rock345 kV135 km Midamerican Energy CoIA, SD
Groton – Watertown345 kV113 km Owner not reportedSD
White – Split Rock345 kV95.0 km Owner not reportedSD
Split Rock345 kV83.8 km Owner not reportedMN, SD
White – Watertown345 kV71.5 km Otter Tail Power CoSD
Big Stone South345 kV49.9 km Otter Tail Power CoSD
Big Stone South345 kV48.9 km Otter Tail Power CoSD
Substation names not reported345 kV39.7 km Otter Tail Power CoSD
Brookings County345 kV30.7 km Otter Tail Power CoSD, MN
Brookings County345 kV26.3 km Otter Tail Power CoSD
White – Deer Creek Station345 kV1.0 km Otter Tail Power CoSD
White – Brookings County345 kV0.8 km Otter Tail Power CoSD
White – Brookings County345 kV0.7 km Otter Tail Power CoSD
Deer Creek Station345 kV0.1 km Otter Tail Power CoSD
Stegall230 kV205 km Black Hills Power, Inc.SD, NE
Bismarck – Glenham230 kV153 km Montana-dakota Utilities CoND, SD
Fort Thompson – Fort Randall230 kV141 km WAPA-- Western Area Power AdministrationSD
Fort Randall230 kV135 km Owner not reportedNE, SD
New Underwood – Wayside230 kV129 km WAPA-- Western Area Power AdministrationNE, SD
Fort Thompson230 kV122 km WAPA-- Western Area Power AdministrationSD

Source: Homeland Infrastructure Foundation-Level Data (HIFLD), Electric Power Transmission Lines. HIFLD Open closed in September 2025; this is the last public version (August 2025). Lines are mapped from imagery and utility filings; some voltages and owners are not reported. Lengths are route lengths of the mapped sections. Interconnection queues Β· US power plants