πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Transmission lines β€Ί Texas

OCTARY USA Β· TRANSMISSION

Transmission lines in Texas

The high-voltage lines that carry electricity from power plants to cities, with voltage, owner and the substations at each end. Click a state to drill down, or a line on the map for details.

Line sections7,040mapped segments
Route length95,946 km59,618 mi
345 kV and above26,308 kmthe backbone
Owners93utilities and others

Map

Loading lines…
500 kV345 kV220–287 kV100–161 kVUnder 100 kVVoltage not reported

Longest high-voltage lines

220 kV and above, highest voltage first
BetweenVoltageLengthOwnerState
Hartburg500 kV207 km Owner not reportedLA, TX
Leach – Hartburg500 kV105 km Entergy Texas Inc.TX
Hartburg – Cypress500 kV51.4 km Entergy Texas Inc.TX
Hartburg500 kV29.4 km Entergy Louisiana LLCLA, TX
Hartburg500 kV1.0 km Deep East Texas Elec Coop IncTX
Hartburg500 kV1.0 km Deep East Texas Elec Coop IncTX
Substation names not reported500 kV0.2 km Deep East Texas Elec Coop IncTX
Substation names not reported345 kV344 km Owner not reportedTX
Substation names not reported345 kV264 km Oncor Electric Delivery Co.TX
Substation names not reported345 kV264 km Oncor Electric Delivery Co.TX
Substation names not reported345 kV260 km Southwestern Public Service CoTX
Eddy Ac-dc-ac Tie345 kV254 km Owner not reportedTX, NM
Sotex5345 kV226 km AEP Texas Central CompanyTX
Sotex5345 kV223 km Owner not reportedTX
Sotex5345 kV223 km Owner not reportedTX
Tonkawa345 kV214 km Oncor Electric Delivery Company LLCTX
Substation names not reported345 kV198 km AEP Texas Central CompanyTX
Brown – Killeen345 kV197 km Oncor Electric Delivery Company LLCTX
Brown – Killeen345 kV197 km Oncor Electric Delivery Company LLCTX
Hitchland345 kV190 km Owner not reportedKS, TX
Abilene Mulberry Creek345 kV186 km AEP Texas North CompanyTX
Substation names not reported345 kV179 km AEP Texas North CompanyTX
Substation names not reported345 kV176 km Big Country Electric Coop, IncTX
Tesla345 kV176 km Greenbelt Electric Coop, IncTX
Lobo – San Miguel345 kV170 km AEP Texas Central CompanyTX

Line length by state

Click a state to drill down.

Largest owners

By route length in this view. Click to map their lines.

Source: Homeland Infrastructure Foundation-Level Data (HIFLD), Electric Power Transmission Lines. HIFLD Open closed in September 2025; this is the last public version (August 2025). Lines are mapped from imagery and utility filings; some voltages and owners are not reported. Lengths are route lengths of the mapped sections. Interconnection queues Β· US power plants