United States › Grid › Interconnection queues › South Dakota
ONSHORE WIND · SPPOnshore wind project GEN-2016-087, Campbell County
Onshore wind project GEN-2016-087, Campbell County is a 98.9 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Campbell County, South Dakota, connecting to WAPA.
Queue statusConsented
- PlanningQueued Jul 2016 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2016-087
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Campbell County 230 kV line
- Location
- Campbell County, South Dakota
- Technology
- Wind: 98.9 MW
- Total requested
- 98.9 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 25 July 2016
- Proposed online date
- December 2026
Location
Marker shows the centre of Campbell County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Campbell County
- Coal project BHBE G11, Campbell CountyCoal · 475 MW · agreement signed
- Coal project BHBE G4, Campbell CountyCoal · 300 MW · agreement signed
- Solar project BHBE G19, Campbell CountySolar · 300 MW · agreement signed
- Coal project BHBE G1, Campbell CountyCoal · 250 MW · agreement signed
- Onshore wind project BHBE G21, Campbell CountyOnshore wind · 200 MW · agreement signed
- Onshore wind project BHBE G7, Campbell CountyOnshore wind · 200 MW · agreement signed
- Coal project BHBE G2, Campbell CountyCoal · 100 MW · agreement signed
- Coal project BHBE G5, Campbell CountyCoal · 100 MW · agreement signed
- Coal project BHBE G3, Campbell CountyCoal · 40.0 MW · agreement signed
- Onshore wind project GI-1001, Campbell CountyOnshore wind · 99.0 MW · built
- Coal project GI-0517, Campbell CountyCoal · 700 MW · withdrawn
- Coal project GI-0702, Campbell CountyCoal · 700 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem