WIND + STORAGE · MISOWind + storage project J3468, Day County
Wind + storage project J3468, Day County is a 300 MW wind + storage request in interconnection study in the MISO interconnection queue, in Day County, South Dakota, connecting to OTTER TAIL POWER COMPANY.
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3468
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Ellendale - Twin Brooks 345.0kV
- Location
- Day County, South Dakota
- Technology
- Wind: 300 MW · Battery
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 12 April 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Day County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Day County
- Onshore wind project J3279, Day CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J933, Day CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1521, Day CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2019-060, Day CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2015-097, Day CountyOnshore wind · 100 MW · withdrawn
- Battery storage project GEN-2019-032, Day CountyBattery storage · 63.1 MW · withdrawn
- Solar project GEN-2019-057, Day CountySolar · 63.1 MW · withdrawn
- Onshore wind project GI-0302, Day CountyOnshore wind · 49.0 MW · withdrawn