United States › Grid › Interconnection queues › South Dakota
ONSHORE WIND · MISOOnshore wind project J722, Codington County
Onshore wind project J722, Codington County is a 200 MW onshore wind request under construction in the MISO interconnection queue, in Codington County, South Dakota, connecting to OTTER TAIL POWER COMPANY.
Queue statusUnder construction
- PlanningQueued Jun 2017 (completed)
- ConsentedOct 2021 (completed)
- Construction (current stage)
- OperatingTarget Sep 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J722
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Big Stone South 230kV Substation
- Location
- Codington County, South Dakota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 16 June 2017
- Agreement signed
- 4 October 2021
- Proposed online date
- September 2023
Location
Marker shows the centre of Codington County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Codington County
- Surplus; J442Other · 120 MW · in study
- Surplus; G736Other · 120 MW · in study
- Onshore wind project J436, Codington CountyOnshore wind · 150 MW · built
- Onshore wind project J437, Codington CountyOnshore wind · 150 MW · built
- Other project GI-0219, Codington CountyOther · 7.5 MW · built
- Onshore wind project J773, Codington CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project GI-0118, Codington CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GI-0103, Codington CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GI-0902, Codington CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J133, Codington CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J721, Codington CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J774, Codington CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem