United States › Grid › Interconnection queues › South Dakota

OTHER · MISO

Surplus; G736

Surplus; G736 is a 120 MW other request in interconnection study in the MISO interconnection queue, in Codington County, South Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1046
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Big Stone South 230kV
Location
Codington County, South Dakota
Technology
Other: 120 MW · Battery
Total requested
120 MW
Queue status
Active
Entered queue
13 October 2023
Proposed online date
November 2026

Location

Marker shows the centre of Codington County; the queue data does not give exact sites.

Power plants in South Dakota · Transmission lines in South Dakota

Other requests in Codington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem