SOLAR · WESTSolar project BHBE G22, Meade County
Solar project BHBE G22, Meade County is a 20.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Meade County, South Dakota, connecting to Black Hills Power.
Queue statusConsented
- PlanningQueued Oct 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- BHBE G22
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Black Hills Power
- Connection point (POI)
- Lange-Lookout Tap
- Location
- Meade County, South Dakota
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- NRIS and ERIS
- Study phase
- Draft LGIA
- Queue status
- Active
- Entered queue
- 5 October 2022
- Proposed online date
- January 2024
Location
Marker shows the centre of Meade County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Meade County
- Solar project BHBE G15, Meade CountySolar · 80.0 MW · agreement signed
- Solar project GEN-2024-283, Meade CountySolar · 150 MW · in study
- Solar project GEN-2024-282, Meade CountySolar · 150 MW · in study
- Onshore wind project GI-0810, Meade CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2017-098, Meade CountyOnshore wind · 200 MW · withdrawn
- Solar project GI-1402, Meade CountySolar · 200 MW · withdrawn
- Onshore wind project GI-0929, Meade CountyOnshore wind · 120 MW · withdrawn
- Solar project GEN-2022-067, Meade CountySolar · 85.0 MW · withdrawn