πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· WEST

Onshore wind project BHBE G8, Meade County

Onshore wind project BHBE G8, Meade County is a 50.0 MW onshore wind request withdrawn in the West interconnection queue, in Meade County, South Dakota, connecting to Black Hills Power.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
BHBE G8
Grid region
West (non-ISO utilities)
Utility / transmission owner
Black Hills Power
Developer
DEGS Wind I
Connection point (POI)
Lange-Lookout 230 kV line
Location
Meade County, South Dakota
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
LGIA Executed - Suspended-Terminated
Queue status
Withdrawn
Entered queue
4 February 2009
Proposed online date
December 2010

Location

Marker shows the centre of Meade County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Meade County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem