United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

SOLAR Β· SPP

Solar project GEN-2022-067, Meade County

Solar project GEN-2022-067, Meade County is a 85.0 MW solar request withdrawn in the SPP interconnection queue, in Meade County, South Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-067
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Faith - Maurine 115 kV Substation
Location
Meade County, South Dakota
Technology
Solar: 85.0 MW
Total requested
85.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
5 August 2022
Proposed online date
January 2028
Withdrawn
November 2023

Location

Marker shows the centre of Meade County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Meade County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem