United States › Grid › Interconnection queues › South Dakota
SOLAR · WESTSolar project BHBE G20, Dawes County
Solar project BHBE G20, Dawes County is a 250 MW solar request with a signed interconnection agreement in the West interconnection queue, in Dawes County, South Dakota, connecting to Black Hills Power.
Queue statusConsented
- PlanningQueued Jul 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- BHBE G20
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Black Hills Power
- Connection point (POI)
- West Hills - Stegall 230 kV line
- Location
- Dawes County, South Dakota
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- Draft LGIA
- Queue status
- Active
- Entered queue
- 25 July 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Dawes County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem