Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown18519.7 GW
Active in queue19.7 GW185 requests
Agreement signed8,251 MW65 requests
Withdrawn59480.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

185 requests ยท page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AH1-680, Carroll County
Gas ยท Chestnut Run Energy LLC
1,300 MWIn study Carroll, OHPJM Apr 2025
Trumbull Energy Center
Gas
940 MWAgreement signed Trumbull, OHPJM Oct 2015target 2026
Solar + storage project AJ1-008, Clermont County
Solar + storage
800 MWIn study Clermont, OHPJM May 2023target 2028
Gas project AH1-711, Wood County
Gas ยท Troy Energy, LLC
408 MWIn study Wood, OHPJM Apr 2025
West Lorain Power Plant 345 kV
Gas
406 MWAgreement signed Lorain, OHPJM Sep 2020target 2031
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Yellow Wood Solar Energy Center
Solar
300 MWAgreement signed Clinton, OHPJM Mar 2019target 2026
Butterfly Meadows
Solar ยท Butterfly Meadows Solar Project, LLC
300 MWIn study Van Wert, OHPJM Sep 2020target 2024
Firelands Wind
Onshore wind
298 MWAgreement signed Erie, OHPJM Mar 2017target 2027
Solar project AI2-081, Logan County
Solar
271 MWIn study Logan, OHPJM Feb 2023target 2025
Battery storage project AI1-167, Clermont County
Battery storage
250 MWIn study Clermont, OHPJM Sep 2022target 2028
Cadence Solar Energy Center
Solar
240 MWAgreement signed Union, OHPJM Mar 2018target 2026
Solar project AH1-055, Jackson County
Solar ยท Furnace Solar, LLC
220 MWIn study Jackson, OHPJM Feb 2025target 2026
Eastern Cottontail Solar
Solar
220 MWAgreement signed Fairfield, OHPJM Jan 2019target 2028
Fountain Point Solar
Solar ยท Fountain Point Solar Energy LLC
207 MWIn study Union, OHPJM Aug 2018target 2021
South Branch Solar
Solar
205 MWPaused / redesign Hancock, OHPJM Aug 2017target 2025
Solar project AH1-580, Harrison County
Solar ยท Energy Pastures Solar Project, LLC
200 MWIn study Harrison, OHPJM Mar 2025target 2025
Flint Grid
Battery storage
200 MWAgreement signed Licking, OHPJM Jul 2019target 2027
Solar project AG2-104, Madison County
Solar ยท Oak Run Solar Project, LLC
200 MWIn study Madison, OHPJM Mar 2025target 2025
Battery storage project AG2-329, Wyandot County
Battery storage ยท Wombat Solar LLC
200 MWIn study Wyandot, OHPJM Mar 2025target 2024
Pleasant Prairie Solar Energy Center
Solar
200 MWAgreement signed Franklin, OHPJM Mar 2019target 2027
Solar project AI1-103, Champaign County
Solar
200 MWIn study Champaign, OHPJM Aug 2022target 2029
Onshore wind project AI1-168, Coshocton County
Onshore wind
200 MWIn study Coshocton, OHPJM Sep 2022target 2027
Solar project AG2-082, Harrison County
Solar ยท Energy Pastures Solar Project, LLC
200 MWIn study Harrison, OHPJM Mar 2025target 2024
CG Fulton County
Solar
199 MWAgreement signed Fulton, OHPJM Sep 2019target 2028
Solar project AH2-168, Madison County
Solar
185 MWIn study Madison, OHPJM Mar 2022target 2025
Sloopy Solar Energy Center
Solar
180 MWAgreement signed Clark, OHPJM Mar 2019target 2028
Solar project AH1-537, Highland County
Solar ยท Riverlake Energy, LLC
179 MWIn study Highland, OHPJM Mar 2025target 2025
Kingwood Solar
Solar
175 MWAgreement signed Greene, OHPJM Sep 2017target 2026
Solar project AI2-028, Union County
Solar
160 MWIn study Union, OHPJM Dec 2022target 2026
Springwater Solar
Solar
155 MWAgreement signed Madison, OHPJM Sep 2019target 2027
Harvey Solar I
Solar
150 MWAgreement signed Licking, OHPJM Mar 2018target 2028
Wild Grains Solar
Solar
150 MWAgreement signed Van Wert, OHPJM Oct 2019target 2027
Palomino Solar
Solar
150 MWAgreement signed Highland, OHPJM Aug 2020target 2027
Solar + storage project AI1-100, Belmont County
Solar + storage
150 MWIn study Belmont, OHPJM Aug 2022target 2025
Solar project AI2-035, Putnam County
Solar
150 MWIn study Putnam, OHPJM Jan 2023target 2027
Battery storage project AH2-228, Pickaway County
Battery storage
150 MWIn study Pickaway, OHPJM Mar 2022target 2026
Kensington Solar
Solar
145 MWPaused / redesign Columbiana, OHPJM Mar 2019target 2026
Grover Hill Wind Project
Onshore wind
140 MWAgreement signed Paulding, OHPJM Sep 2018target 2026
Gas project H037, Lucas County
Gas
135 MWAgreement signed Lucas, OHMISO May 2008target 2010
Highland 3 Solar
Solar
130 MWAgreement signed Highland, OHPJM Sep 2019target 2030
South Branch Solar
Solar
130 MWAgreement signed Hancock, OHPJM Mar 2020target 2026
Harvey Solar I
Solar
128 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Vinton Solar
Solar
125 MWAgreement signed Vinton, OHPJM Oct 2016target 2027
Border Basin
Solar
120 MWAgreement signed Hancock, OHPJM Sep 2018target 2026
Canal Road
Solar
120 MWAgreement signed Wayne, OHPJM Mar 2020target 2027
Solar + storage project AI1-074, Jackson County
Solar + storage
120 MWIn study Jackson, OHPJM Jul 2022target 2027
Solar project AH2-345, Lorain County
Solar
120 MWIn study Lorain, OHPJM Mar 2022target 2025
Tymochtee Solar
Solar
120 MWAgreement signed Wyandot, OHPJM Sep 2019target 2026
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)