🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Springwater Solar

Springwater Solar is a 155 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Madison County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-228
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Beatty-Greene 345 kV
Location
Madison County, Ohio
Technology
Solar: 155 MW
Total requested
155 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
27 September 2019
Proposed online date
August 2027

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem