Oak Run Solar Project

Oak Run Solar Project is a 400 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Madison County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Aug 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-125
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville-Flatlick 765 kV
Location
Madison County, Ohio
Technology
Solar: 400 MW
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
31 August 2020
Proposed online date
December 2030

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.