🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Solar project AI2-328, Madison County

Solar project AI2-328, Madison County is a 100 MW solar request in interconnection study in the PJM interconnection queue, in Madison County, Ohio, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI2-328
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville-Flatlick 765 kV
Location
Madison County, Ohio
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
2 March 2023
Proposed online date
December 2026

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem