United States › Grid › Interconnection queues › Ohio
BATTERY STORAGE · PJMBattery storage project AG2-329, Wyandot County
Battery storage project AG2-329, Wyandot County is a 200 MW battery storage request in interconnection study in the PJM interconnection queue, in Wyandot County, Ohio, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AG2-329
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- Wombat Solar LLC
- Connection point (POI)
- S Berwick - Galion 345 kV
- Location
- Wyandot County, Ohio
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 4 March 2025
- Proposed online date
- December 2024
Location
Marker shows the centre of Wyandot County; the queue data does not give exact sites.
Other requests in Wyandot County
- Tymochtee SolarSolar · 120 MW · agreement signed
- Onshore wind project Y1-030, Wyandot CountyOnshore wind · 100 MW · withdrawn
- Battery storage project AG2-148, Wyandot CountyBattery storage · 86.0 MW · withdrawn
- Solar project AH1-339, Wyandot CountySolar · 80.0 MW · withdrawn
- Solar project X1-033, Wyandot CountySolar · 12.0 MW · withdrawn
- Other project Y2-057, Wyandot CountyOther · 3.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem