BATTERY STORAGE Β· PJMBattery storage project AG2-148, Wyandot County
Battery storage project AG2-148, Wyandot County is a 86.0 MW battery storage request withdrawn in the PJM interconnection queue, in Wyandot County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG2-148
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Developer
- Armadillo Solar LLC
- Connection point (POI)
- S Berwick - Galion 345 kV
- Location
- Wyandot County, Ohio
- Technology
- Battery: 86.0 MW
- Total requested
- 86.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 5 March 2025
- Proposed online date
- December 2024
- Withdrawn
- November 2025
Location
Marker shows the centre of Wyandot County; the queue data does not give exact sites.
Other requests in Wyandot County
- Tymochtee SolarSolar Β· 120 MW Β· agreement signed
- Battery storage project AG2-329, Wyandot CountyBattery storage Β· 200 MW Β· in study
- Onshore wind project Y1-030, Wyandot CountyOnshore wind Β· 100 MW Β· withdrawn
- Solar project AH1-339, Wyandot CountySolar Β· 80.0 MW Β· withdrawn
- Solar project X1-033, Wyandot CountySolar Β· 12.0 MW Β· withdrawn
- Other project Y2-057, Wyandot CountyOther Β· 3.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem