πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

BATTERY STORAGE Β· PJM

Battery storage project AG2-148, Wyandot County

Battery storage project AG2-148, Wyandot County is a 86.0 MW battery storage request withdrawn in the PJM interconnection queue, in Wyandot County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-148
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Armadillo Solar LLC
Connection point (POI)
S Berwick - Galion 345 kV
Location
Wyandot County, Ohio
Technology
Battery: 86.0 MW
Total requested
86.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
5 March 2025
Proposed online date
December 2024
Withdrawn
November 2025

Location

Marker shows the centre of Wyandot County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Wyandot County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem