United States › Grid › Interconnection queues › Ohio
SOLAR · PJMSouth Branch Solar
South Branch Solar is a 130 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Hancock County, Ohio, connecting to AEP.
Queue statusConsented
- PlanningQueued Mar 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF2-375
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Ebersole-Fostoria 138 kV
- Location
- Hancock County, Ohio
- Technology
- Solar: 130 MW
- Total requested
- 130 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 31 March 2020
- Proposed online date
- February 2026
Location
Marker shows the centre of Hancock County; the queue data does not give exact sites.
Other requests in Hancock County
- Border BasinSolar · 120 MW · agreement signed
- Solar + storage project AH2-346, Hancock CountySolar + storage · 47.5 MW · in study
- South Branch SolarSolar · 205 MW · suspended
- South Branch SolarSolar · 46.0 MW · suspended
- Granger Electric of Hancock CountyOther · 3.0 MW · built
- Battery storage project AG2-375, Hancock CountyBattery storage · 500 MW · withdrawn
- Onshore wind project W3-012, Hancock CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project W3-011, Hancock CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project X2-058, Hancock CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project V4-015, Hancock CountyOnshore wind · 66.6 MW · withdrawn
- Onshore wind project W2-001, Hancock CountyOnshore wind · 66.6 MW · withdrawn
- Solar + storage project AG2-547, Hancock CountySolar + storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem