BATTERY STORAGE Β· PJM

Battery storage project AG2-375, Hancock County

Battery storage project AG2-375, Hancock County is a 500 MW battery storage request withdrawn in the PJM interconnection queue, in Hancock County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-375
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Foster Energy Storage LLC
Connection point (POI)
Fostoria Central 345 kV
Location
Hancock County, Ohio
Technology
Battery: 500 MW
Total requested
500 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
29 March 2021
Proposed online date
November 2024
Withdrawn
July 2025

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem