United States › Grid › Interconnection queues › Ohio
SOLAR + STORAGE · PJMSolar + storage project AH2-346, Hancock County
Solar + storage project AH2-346, Hancock County is a 47.5 MW solar + storage request in interconnection study in the PJM interconnection queue, in Hancock County, Ohio, connecting to AEP.
Queue statusIn planning
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-346
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- East Arlington 69 kV
- Location
- Hancock County, Ohio
- Technology
- Solar: 47.5 MW · Battery
- Total requested
- 47.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 10 March 2022
- Proposed online date
- March 2025
Location
Marker shows the centre of Hancock County; the queue data does not give exact sites.
Other requests in Hancock County
- South Branch SolarSolar · 130 MW · agreement signed
- Border BasinSolar · 120 MW · agreement signed
- South Branch SolarSolar · 205 MW · suspended
- South Branch SolarSolar · 46.0 MW · suspended
- Granger Electric of Hancock CountyOther · 3.0 MW · built
- Battery storage project AG2-375, Hancock CountyBattery storage · 500 MW · withdrawn
- Onshore wind project W3-012, Hancock CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project W3-011, Hancock CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project X2-058, Hancock CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project V4-015, Hancock CountyOnshore wind · 66.6 MW · withdrawn
- Onshore wind project W2-001, Hancock CountyOnshore wind · 66.6 MW · withdrawn
- Solar + storage project AG2-547, Hancock CountySolar + storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem