ONSHORE WIND Β· PJMOnshore wind project W3-011, Hancock County
Onshore wind project W3-011, Hancock County is a 300 MW onshore wind request withdrawn in the PJM interconnection queue, in Hancock County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandonedSep 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- W3-011
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- East Lima-Fostoria Central 345kV
- Location
- Hancock County, Ohio
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 August 2010
- Proposed online date
- December 2014
- Withdrawn
- September 2011
Location
Marker shows the centre of Hancock County; the queue data does not give exact sites.
Other requests in Hancock County
- South Branch SolarSolar Β· 130 MW Β· agreement signed
- Border BasinSolar Β· 120 MW Β· agreement signed
- Solar + storage project AH2-346, Hancock CountySolar + storage Β· 47.5 MW Β· in study
- South Branch SolarSolar Β· 205 MW Β· suspended
- South Branch SolarSolar Β· 46.0 MW Β· suspended
- Granger Electric of Hancock CountyOther Β· 3.0 MW Β· built
- Battery storage project AG2-375, Hancock CountyBattery storage Β· 500 MW Β· withdrawn
- Onshore wind project W3-012, Hancock CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project X2-058, Hancock CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project V4-015, Hancock CountyOnshore wind Β· 66.6 MW Β· withdrawn
- Onshore wind project W2-001, Hancock CountyOnshore wind Β· 66.6 MW Β· withdrawn
- Solar + storage project AG2-547, Hancock CountySolar + storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem