🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Cadence Solar Energy Center

Cadence Solar Energy Center is a 240 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Union County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AD2-093
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville 345kV
Location
Union County, Ohio
Technology
Solar: 240 MW
Total requested
240 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
21 March 2018
Proposed online date
March 2026

Location

Marker shows the centre of Union County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Union County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem