United States › Grid › Interconnection queues › Ohio

BATTERY STORAGE · PJM

Cadence Energy Storage

Cadence Energy Storage is a 50.0 MW battery storage request suspended in the PJM interconnection queue, in Union County, Ohio, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AD2-096
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Marysville 345kV
Location
Union County, Ohio
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
21 March 2018
Proposed online date
March 2026

Location

Marker shows the centre of Union County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Union County