United States › Grid › Interconnection queues › Ohio
SOLAR + STORAGE · PJMSolar + storage project AI1-100, Belmont County
Solar + storage project AI1-100, Belmont County is a 150 MW solar + storage request in interconnection study in the PJM interconnection queue, in Belmont County, Ohio, connecting to AEP.
Queue statusIn planning
- PlanningQueued Aug 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-100
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Somerton - Norton 138 kV
- Location
- Belmont County, Ohio
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 30 August 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Belmont County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem