🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Highland 3 Solar

Highland 3 Solar is a 130 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Highland County, Ohio, connecting to Dayton.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-283
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dayton
Connection point (POI)
Stuart-Clinton 345 kV
Location
Highland County, Ohio
Technology
Solar: 130 MW
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
30 September 2019
Proposed online date
May 2030

Location

Marker shows the centre of Highland County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Highland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem