United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AF1-034, Highland County
Solar project AF1-034, Highland County is a 300 MW solar request withdrawn in the PJM interconnection queue, in Highland County, Ohio, connecting to Dayton.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2019 (completed)
- Withdrawn / abandonedJun 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF1-034
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Connection point (POI)
- Clinton-Stuart 345 kV
- Location
- Highland County, Ohio
- Technology
- Solar: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 22 May 2019
- Proposed online date
- November 2021
- Withdrawn
- June 2019
Location
Marker shows the centre of Highland County; the queue data does not give exact sites.
Other requests in Highland County
- Palomino SolarSolar Β· 150 MW Β· agreement signed
- Highland 3 SolarSolar Β· 130 MW Β· agreement signed
- Nuthatch Solar 5Solar Β· 100 MW Β· agreement signed
- Palomino SolarSolar Β· 50.0 MW Β· agreement signed
- Solar project AH1-537, Highland CountySolar Β· 179 MW Β· in study
- Solar project AH2-159, Highland CountySolar Β· 49.0 MW Β· in study
- Solar project AH2-160, Highland CountySolar Β· 20.0 MW Β· in study
- Highland County SolarSolar Β· 400 MW Β· built
- Willowbrook SolarSolar Β· 150 MW Β· built
- Battery storage project AH1-766, Highland CountyBattery storage Β· 205 MW Β· withdrawn
- Solar project AC2-042, Highland CountySolar Β· 200 MW Β· withdrawn
- Solar project AD2-010, Highland CountySolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem