United States › Grid › Interconnection queues › Ohio
SOLAR · PJMNuthatch Solar 5
Nuthatch Solar 5 is a 100 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Highland County, Ohio, connecting to Dayton.
Queue statusConsented
- PlanningQueued Sep 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget May 2030 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF1-282
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Connection point (POI)
- Stuart-Clinton 345 kV
- Location
- Highland County, Ohio
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 30 September 2019
- Proposed online date
- May 2030
Location
Marker shows the centre of Highland County; the queue data does not give exact sites.
Other requests in Highland County
- Palomino SolarSolar · 150 MW · agreement signed
- Highland 3 SolarSolar · 130 MW · agreement signed
- Palomino SolarSolar · 50.0 MW · agreement signed
- Solar project AH1-537, Highland CountySolar · 179 MW · in study
- Solar project AH2-159, Highland CountySolar · 49.0 MW · in study
- Solar project AH2-160, Highland CountySolar · 20.0 MW · in study
- Highland County SolarSolar · 400 MW · built
- Willowbrook SolarSolar · 150 MW · built
- Solar project AF1-034, Highland CountySolar · 300 MW · withdrawn
- Battery storage project AH1-766, Highland CountyBattery storage · 205 MW · withdrawn
- Solar project AC2-042, Highland CountySolar · 200 MW · withdrawn
- Solar project AD2-010, Highland CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem