SOLAR · PJM

Palomino Solar

Palomino Solar is a 50.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Highland County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Mar 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-440
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Hillsboro-Middleboro 138 kV
Location
Highland County, Ohio
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
31 March 2020
Proposed online date
August 2027

Location

Marker shows the centre of Highland County; the queue data does not give exact sites.