Battery storage project AI1-167, Clermont County

Battery storage project AI1-167, Clermont County is a 250 MW battery storage request in interconnection study in the PJM interconnection queue, in Clermont County, Ohio, connecting to DEOK.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-167
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DEOK
Connection point (POI)
Cedarville 138 kV
Location
Clermont County, Ohio
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
9 September 2022
Proposed online date
December 2028

Location

Marker shows the centre of Clermont County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Clermont County