🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

COAL · MISO

Coal project G989, Clermont County

Coal project G989, Clermont County is a 330 MW coal request built and operating in the MISO interconnection queue, in Clermont County, Ohio.

Queue statusOperating
  1. PlanningQueued Mar 2008 (completed)
  2. ConsentedJun 2008 (completed)
  3. Construction (completed)
  4. OperatingDec 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G989
Grid region
MISO (Midcontinent)
Connection point (POI)
Zimmer 345 kV Station
Location
Clermont County, Ohio
Technology
Coal: 330 MW
Total requested
330 MW
Study phase
SPA - SIS
Queue status
Operational
Entered queue
21 March 2008
Agreement signed
2 June 2008
Proposed online date
December 2010
Came online
December 2010

Location

Marker shows the centre of Clermont County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Clermont County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem