United States › Grid › Interconnection queues › Ohio

SOLAR · PJM

Clermont County Solar Project

Clermont County Solar Project is a 100 MW solar request suspended in the PJM interconnection queue, in Clermont County, Ohio, connecting to DEOK.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE2-318
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DEOK
Connection point (POI)
Ford-Cedarville 138 kV
Location
Clermont County, Ohio
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
31 March 2019
Proposed online date
December 2025

Location

Marker shows the centre of Clermont County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Clermont County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem