United States › Grid › Interconnection queues › Ohio
SOLAR · PJMClermont County Solar Project
Clermont County Solar Project is a 100 MW solar request suspended in the PJM interconnection queue, in Clermont County, Ohio, connecting to DEOK.
Queue statusPaused / redesign
- PlanningQueued Mar 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AE2-318
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DEOK
- Connection point (POI)
- Ford-Cedarville 138 kV
- Location
- Clermont County, Ohio
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 31 March 2019
- Proposed online date
- December 2025
Location
Marker shows the centre of Clermont County; the queue data does not give exact sites.
Other requests in Clermont County
- Solar + storage project AJ1-008, Clermont CountySolar + storage · 800 MW · in study
- Battery storage project AI1-167, Clermont CountyBattery storage · 250 MW · in study
- Solar project AI2-348, Clermont CountySolar · 17.4 MW · in study
- Clermont County Solar ProjectBattery storage · 52.2 MW · suspended
- Coal project G989, Clermont CountyCoal · 330 MW · built
- Nestlewood SolarSolar · 70.0 MW · built
- Coal project G990, Clermont CountyCoal · 52.0 MW · built
- Zimmer StationCoal · 20.0 MW · built
- Nestlewood SolarSolar · 10.0 MW · built
- Beckjord Battery #1Battery storage · 2.0 MW · built
- Beckjord Battery #2Battery storage · 2.0 MW · built
- Battery storage project AE2-329, Clermont CountyBattery storage · 209 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem