United States › Grid › Interconnection queues › Ohio
ONSHORE WIND · PJMFirelands Wind
Firelands Wind is a 298 MW onshore wind request with a signed interconnection agreement in the PJM interconnection queue, in Erie County, Ohio, connecting to ATSI.
Queue statusConsented
- PlanningQueued Mar 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AC2-103
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Beaver-Davis Besse 345 kV I
- Location
- Erie County, Ohio
- Technology
- Wind: 298 MW
- Total requested
- 298 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 10 March 2017
- Proposed online date
- June 2027
Location
Marker shows the centre of Erie County; the queue data does not give exact sites.
Other requests in Erie County
- Wheatsborough SolarSolar · 125 MW · built
- Erie County LandfillOther · 0.8 MW · built
- Solar project AD2-156, Erie CountySolar · 100 MW · withdrawn
- Onshore wind project W3-059A_AT6, Erie CountyOnshore wind · 99.0 MW · withdrawn
- Onshore wind project J164, Erie CountyOnshore wind · 99.0 MW · withdrawn
- Solar + storage project AH1-417, Erie CountySolar + storage · 50.0 MW · withdrawn
- Onshore wind project G652, Erie CountyOnshore wind · 48.0 MW · withdrawn
- Battery storage project AG1-425, Erie CountyBattery storage · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem