United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

ONSHORE WIND Β· MISO

Onshore wind project G652, Erie County

Onshore wind project G652, Erie County is a 48.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Erie County, Ohio.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJun 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G652
Grid region
MISO (Midcontinent)
Connection point (POI)
Bellevue - Castalia 69 kV
Location
Erie County, Ohio
Technology
Wind: 48.0 MW
Total requested
48.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
3 July 2006
Agreement signed
15 June 2010
Proposed online date
January 2008

Location

Marker shows the centre of Erie County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Erie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem