πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

ONSHORE WIND Β· MISO

Onshore wind project J164, Erie County

Onshore wind project J164, Erie County is a 99.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Erie County, Ohio.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. ConsentedJun 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J164
Grid region
MISO (Midcontinent)
Connection point (POI)
FE Beaver - Greenfield 138kV
Location
Erie County, Ohio
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
10 September 2010
Agreement signed
1 June 2011
Proposed online date
December 2014
Withdrawn
June 2011

Location

Marker shows the centre of Erie County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Erie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem