United States › Grid › Interconnection queues › Ohio
SOLAR · PJMSolar project AI1-103, Champaign County
Solar project AI1-103, Champaign County is a 200 MW solar request in interconnection study in the PJM interconnection queue, in Champaign County, Ohio, connecting to Dayton.
Queue statusIn planning
- PlanningQueued Aug 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-103
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dayton
- Connection point (POI)
- Mechanicsburg 138 kV
- Location
- Champaign County, Ohio
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 30 August 2022
- Proposed online date
- December 2029
Location
Marker shows the centre of Champaign County; the queue data does not give exact sites.
Other requests in Champaign County
- Hillclimber SolarSolar · 78.0 MW · agreement signed
- Hillclimber SolarBattery storage · 40.0 MW · agreement signed
- Hillclimber SolarSolar · 38.5 MW · agreement signed
- Solar + storage project AI1-112, Champaign CountySolar + storage · 85.0 MW · in study
- Woodstock SolarSolar · 40.0 MW · suspended
- Clearview Solar ISolar · 99.0 MW · built
- Clearview Solar ISolar · 45.0 MW · built
- Solar project AH1-635, Champaign CountySolar · 200 MW · withdrawn
- Solar project AH1-519, Champaign CountySolar · 200 MW · withdrawn
- Battery storage project AH1-636, Champaign CountyBattery storage · 200 MW · withdrawn
- Buckeye Wind Farm - Phase 1Onshore wind · 200 MW · withdrawn
- Onshore wind project S46, Champaign CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem