BATTERY STORAGE · PJM

Flint Grid

Flint Grid is a 200 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in Licking County, Ohio, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Jul 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-062
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Jug Street 138 kV
Location
Licking County, Ohio
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
31 July 2019
Proposed online date
May 2027

Location

Marker shows the centre of Licking County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Licking County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem