BATTERY STORAGE Β· PJM

Battery storage project AE2-300, Licking County

Battery storage project AE2-300, Licking County is a 200 MW battery storage request withdrawn in the PJM interconnection queue, in Licking County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE2-300
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Location
Licking County, Ohio
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 March 2019
Proposed online date
September 2022
Withdrawn
April 2019

Location

Marker shows the centre of Licking County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Licking County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem