United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AE2-073, Licking County
Solar project AE2-073, Licking County is a 50.0 MW solar request withdrawn in the PJM interconnection queue, in Licking County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2019 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE2-073
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Centerburg 138kV
- Location
- Licking County, Ohio
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 15 February 2019
- Proposed online date
- November 2021
- Withdrawn
- October 2024
Location
Marker shows the centre of Licking County; the queue data does not give exact sites.
Other requests in Licking County
- Flint GridBattery storage Β· 200 MW Β· agreement signed
- Harvey Solar ISolar Β· 150 MW Β· agreement signed
- Harvey Solar ISolar Β· 128 MW Β· agreement signed
- Union Ridge SolarSolar Β· 108 MW Β· agreement signed
- Harvey Solar ISolar Β· 85.0 MW Β· agreement signed
- Solar project AI2-427, Licking CountySolar Β· 26.4 MW Β· in study
- Battery storage project AI2-483, Licking CountyBattery storage Β· 13.4 MW Β· in study
- Battery storage project AE2-300, Licking CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project AH1-550, Licking CountySolar Β· 110 MW Β· withdrawn
- Battery storage project AH1-036, Licking CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project AH1-325, Licking CountyBattery storage Β· 50.0 MW Β· withdrawn
- Solar project AG2-006, Licking CountySolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem