United States โ€บ Grid โ€บ Interconnection queues โ€บ Wisconsin

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Wisconsin

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown11726.6 GW
Active in queue26.6 GW117 requests
Agreement signed3,635 MW26 requests
Withdrawn24049.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

117 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Red Oak Ridge Energy Center
Gas ยท Invenergy
1,211 MWIn study Kenosha, WIMISO Aug 2025target 2027
Gas project E0016, Calumet County
Gas ยท Invenergy
1,211 MWIn study Calumet, WIMISO Aug 2025target 2027
Gas project J4164, Dane County
Gas
1,203 MWIn study Dane, WIMISO Sep 2025target 2030
Gas project J4165, Kenosha County
Gas
1,203 MWIn study Kenosha, WIMISO Sep 2025target 2030
Gas project J4014, Calumet County
Gas
1,203 MWIn study Calumet, WIMISO May 2025target 2030
Replacement; Oak Creek Units 5-8
Gas
1,138 MWIn study Milwaukee, WIMISO Jun 2024target 2027
Gas project J4116, Walworth County
Gas
950 MWIn study Walworth, WIMISO Oct 2025target 2030
Gas project J732, Douglas County
Gas
562 MWUnder construction Douglas, WIMISO Jun 2017target 2023
Gas project J4115, Fond Du Lac County
Gas
525 MWIn study Fond Du Lac, WIMISO Oct 2025target 2028
Gas project J4144, Columbia County
Gas
525 MWIn study Columbia, WIMISO Oct 2025target 2030
Gas project E0037, Sheboygan County
Gas ยท Wisconsin Power and Light Company (WPL)
455 MWIn study Sheboygan, WIMISO Aug 2025target 2025
Gas project E0038, Winnebago County
Gas ยท Wisconsin Power and Light Company (WPL)
455 MWIn study Winnebago, WIMISO Aug 2025target 2025
Solar project J3975, Rusk County
Solar
417 MWIn study Rusk, WIMISO Mar 2025target 2030
Battery storage project J2304, Columbia County
Battery storage
400 MWIn study Columbia, WIMISO Dec 2021target 2024
Solar project J2107, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2099, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2185, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Gas project J2944, Portage County
Gas
350 MWIn study Portage, WIMISO Sep 2022target 2027
Gas project J4028, Walworth County
Gas
324 MWIn study Walworth, WIMISO May 2025target 2027
Replacing 303.5 MW BESS with 303.5 MW COAL; Edgewater Unit 5
Other
304 MWIn study Sheboygan, WIMISO Dec 2024target 2025
Battery storage project J3006, Milwaukee County
Battery storage
300 MWIn study Milwaukee, WIMISO Jul 2025target 2028
Onshore wind project J1781, Iowa County
Onshore wind
300 MWUnder construction Iowa, WIMISO Jun 2020target 2027
Solar project J1730, Dunn County
Solar
300 MWUnder construction Dunn, WIMISO Mar 2022target 2027
Solar project J1513, Waupaca County
Solar
300 MWAgreement signed Waupaca, WIMISO Feb 2022target 2026
Solar project J1410, Dane County
Solar
300 MWUnder construction Dane, WIMISO Apr 2019target 2025
Solar project J1214, Dane County
Solar
300 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Onshore wind project J1773, Lafayette County
Onshore wind
300 MWAgreement signed Lafayette, WIMISO Jun 2020target 2027
Solar project J2446, Dunn County
Solar
300 MWIn study Dunn, WIMISO Sep 2022target 2027
Battery storage project J2423, Columbia County
Battery storage
300 MWIn study Columbia, WIMISO Sep 2022target 2027
Solar project J1573, Portage County
Solar
250 MWAgreement signed Portage, WIMISO Jun 2020target 2026
Onshore wind project J3639, Columbia County
Onshore wind
250 MWIn study Columbia, WIMISO Apr 2024target 2028
Solar project J2870, Sawyer County
Solar
244 MWIn study Sawyer, WIMISO Sep 2022target 2026
Solar project J1502, Juneau County
Solar
225 MWAgreement signed Juneau, WIMISO Jun 2020target 2026
Gas project J2947, Rock County
Gas
205 MWIn study Rock, WIMISO Sep 2022target 2026
Battery storage project J1895, Kenosha County
Battery storage
200 MWIn study Kenosha, WIMISO Oct 2023target 2024
Solar project J2520, Adams County
Solar
200 MWIn study Adams, WIMISO Sep 2022target 2025
Solar + storage project J1779, Dane County
Solar + storage
200 MWAgreement signed Dane, WIMISO Sep 2021target 2027
Solar project J1808, Barron County
Solar
200 MWIn study Barron, WIMISO Jun 2020target 2026
Solar project J1460, Rock County
Solar
200 MWUnder construction Rock, WIMISO Apr 2019target 2025
Solar project J1629, Columbia County
Solar
200 MWAgreement signed Columbia, WIMISO Jun 2020target 2027
Solar project J1943, Columbia County
Solar
200 MWIn study Columbia, WIMISO Aug 2021target 2024
Battery storage project J3784, Ozaukee County
Battery storage
200 MWIn study Ozaukee, WIMISO Apr 2024target 2028
Solar project J2559, Wood County
Solar
200 MWIn study Wood, WIMISO Sep 2022target 2029
Battery storage project J3402, Juneau County
Battery storage
200 MWIn study Juneau, WIMISO Apr 2024target 2028
Solar project J878, Kenosha County
Solar
200 MWUnder construction Kenosha, WIMISO Jun 20172024
Onshore wind project J3204, Clark County
Onshore wind
190 MWIn study Clark, WIMISO Sep 2022target 2025
Onshore wind project J3448, Grant County
Onshore wind
180 MWIn study Grant, WIMISO Apr 2024target 2028
Solar project J4069, Marathon County
Solar
170 MWIn study Marathon, WIMISO Oct 2025target 2030
Gas project J3152, Green County
Gas
160 MWIn study Green, WIMISO Sep 2022target 2027
Solar project J1751, Wood County
Solar
151 MWAgreement signed Wood, WIMISO Apr 2022target 2026
Page 1 of 3

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20142025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)