United States › Grid › Interconnection queues › Wisconsin
GAS · MISOGas project J4014, Calumet County
Gas project J4014, Calumet County is a 1,203 MW gas request in interconnection study in the MISO interconnection queue, in Calumet County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusIn planning
- PlanningQueued May 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4014
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Forest Junction
- Location
- Calumet County, Wisconsin
- Technology
- Gas: 1,203 MW
- Total requested
- 1,203 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 21 May 2025
- Proposed online date
- May 2030
Location
Marker shows the centre of Calumet County; the queue data does not give exact sites.
Other requests in Calumet County
- Gas project E0016, Calumet CountyGas · 1,211 MW · in study
- Gas project J336, Calumet CountyGas · 845 MW · withdrawn
- Gas project J335, Calumet CountyGas · 551 MW · withdrawn
- Other project G102, Calumet CountyOther · 530 MW · withdrawn
- Other project G152, Calumet CountyOther · 530 MW · withdrawn
- Solar project J1775, Calumet CountySolar · 150 MW · withdrawn
- Onshore wind project J3332, Calumet CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project G977, Calumet CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project G611, Calumet CountyOnshore wind · 99.0 MW · withdrawn
- Onshore wind project G590, Calumet CountyOnshore wind · 98.0 MW · withdrawn
- Onshore wind project G334, Calumet CountyOnshore wind · 80.0 MW · withdrawn
- Onshore wind project H090, Calumet CountyOnshore wind · 60.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem