🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wisconsin

GAS · MISO

Gas project E0016, Calumet County

Gas project E0016, Calumet County is a 1,211 MW gas request in interconnection study in the MISO interconnection queue, in Calumet County, Wisconsin, connecting to Wisconsin Electric Power Company.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
E0016
Grid region
MISO (Midcontinent)
Utility / transmission owner
Wisconsin Electric Power Company
Developer
Invenergy
Connection point (POI)
Forrest Junction
Location
Calumet County, Wisconsin
Technology
Gas: 1,211 MW
Total requested
1,211 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Active; Post GIA Status: Not started
Queue status
Active
Entered queue
6 August 2025
Proposed online date
December 2027

Location

Marker shows the centre of Calumet County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Calumet County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem