United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
ONSHORE WIND Β· MISOOnshore wind project J3332, Calumet County
Onshore wind project J3332, Calumet County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Calumet County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3332
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Forest Junction - Cypress 345.0kV
- Location
- Calumet County, Wisconsin
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 17 April 2024
- Proposed online date
- May 2028
- Withdrawn
- September 2025
Location
Marker shows the centre of Calumet County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Calumet County
- Gas project E0016, Calumet CountyGas Β· 1,211 MW Β· in study
- Gas project J4014, Calumet CountyGas Β· 1,203 MW Β· in study
- Gas project J336, Calumet CountyGas Β· 845 MW Β· withdrawn
- Gas project J335, Calumet CountyGas Β· 551 MW Β· withdrawn
- Other project G102, Calumet CountyOther Β· 530 MW Β· withdrawn
- Other project G152, Calumet CountyOther Β· 530 MW Β· withdrawn
- Solar project J1775, Calumet CountySolar Β· 150 MW Β· withdrawn
- Onshore wind project G977, Calumet CountyOnshore wind Β· 101 MW Β· withdrawn
- Onshore wind project G611, Calumet CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Onshore wind project G590, Calumet CountyOnshore wind Β· 98.0 MW Β· withdrawn
- Onshore wind project G334, Calumet CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Onshore wind project H090, Calumet CountyOnshore wind Β· 60.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem