Onshore wind project G590, Calumet County

Onshore wind project G590, Calumet County is a 98.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Calumet County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJul 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G590
Grid region
MISO (Midcontinent)
Connection point (POI)
Tecumseh Road 138 kV Subsation
Location
Calumet County, Wisconsin
Technology
Wind: 98.0 MW
Total requested
98.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
23 January 2006
Agreement signed
18 July 2008
Proposed online date
August 2007

Location

Marker shows the centre of Calumet County; the queue data does not give exact sites.