United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J1460, Rock County

Solar project J1460, Rock County is a 200 MW solar request under construction in the MISO interconnection queue, in Rock County, Wisconsin, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedApr 2023 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1460
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Sunrise 138 kV Substation
Location
Rock County, Wisconsin
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
7 April 2023
Proposed online date
June 2025

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Rock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem